As we are all confused ~ In the Match Programme yesterday Brian Fagan stated that work starts on Monday 17th August 2009 and gave us a taster of the construction timetable as follows:
1st tasks will be to set up site logistics and install the main drainage system around the site.
24th August work will commence on the first of the piled foundation supporting the Main Stand but not much change will be visable.
12th October, foundations will be complete and work will start on the steel framework to form the superstructure of the Main Stand and within a few weeks this will start to take shape.
December ~ the wall cladding and decking out the roof will take place which should be complete for Christmas.
This is the first of a series of information feedbacks and updates will be given in the meantime before completion time On July 5th.
Also noticed that Glen will be interviewing Mr. McGuigan in the near future