.......... CC's ..............
.......... natural spring water bottling plant (Storth branch).
Announcement on Wednesday (local press).
Christies Child wrote:Sorry but my PR agency has been instructed to put an embargo on all future information regarding my companys involvement until our sponsorship package has been watered down due to a co-sponsor bottling out of any deal. Their may be a trickle of information towards the end of next week. However no formal agreement is likely to be signed until spring, at which time events will take their natural course.
Sorry but my PR agency has been instructed to put an embargo on all future information regarding my companys involvement until our sponsorship package has been watered down due to a co-sponsor bottling out of any deal. Their may be a trickle of information towards the end of next week. However no formal agreement is likely to be signed until spring, at which time events will take their natural course.
alwaysright wrote:WOW thats a really exciting photo i can hardly contain myself, in fact i may just sit here all day and look at that really exciting photo
alwaysright wrote:There will be no chance of ground sharing with Lancaster City
marky No.1 wrote:For those of you without yesterdays Match programme:
400 reinforced concrete piles have been driven in to support the stands to a maximum of 15metres (it was going to be 350 but they are obviously allowing for CC)
Total length of piles ~ 3 miles!![]()
Main stand foundations now in place. Stand fabrication to be completed off-site.
... and guess what ~ the steelwork is due to be delivered tomorrow ~ Monday!!
parceldave wrote:marky No.1 wrote:For those of you without yesterdays Match programme:
400 reinforced concrete piles have been driven in to support the stands to a maximum of 15metres (it was going to be 350 but they are obviously allowing for CC)
Total length of piles ~ 3 miles!![]()
Main stand foundations now in place. Stand fabrication to be completed off-site.
... and guess what ~ the steelwork is due to be delivered tomorrow ~ Monday!!
If it weighs more than 30kg's im not taking it.